Who is doing what?
1 ... Purchaser resp. project-owner / 2 ... Engineering company resp. designing
3 ... Construction works / 4 ... Pipe-laying / 5 ... isoplus
| # | Project phases | 1 | 2 | 3 | 4 | 5 |
|---|---|---|---|---|---|---|
| 1 | Construction design, start of design procedure | • | ||||
| 2 | Customer, respectively user acquisition | • | ||||
| 3 | Calculation of required energy for users | • | ||||
| 4 | Hydraulic network-calculation resp. dimensioning | • | ||||
| 5 | First design | • | ||||
| 6 | Getting approvals from local authorities | • | ||||
| 7 | Measurement of designed trenches in lengths and heights | • | ||||
| 8 | Measurement of existing distributing lines | • | ||||
| 9 | Work out of trench design in lengths and heights | • | ||||
| 10 | Work out of material-list for the project | • | ||||
| 11 | Preparing of tender documents | • | ||||
| 12 | Dispatch of performance-description | • | ||||
| 13 | Price calculation of offer and placing of offer in time | • | • | • | ||
| 14 | Work out of project- time schedule | • | • | |||
| 15 | Placing of order | • | ||||
| 16 | Visit of building site before start of works | • | • | • | • | • |
| 17 | Eventually second common measurement of trench after agreement | • | • | |||
| 18 | Work out of pipe-static calculation of buried pipes | • | ||||
| 19 | Demonstration of pipe-static by presenting design for expansion pads | • | ||||
| 20 | Material specification of isoplus-pipes, fittings and accessories | • | ||||
| 21 | Equipment for building site | • | • | |||
| 22 | Marking of foreign pipelines along the new trench | • | • | • | ||
| 23 | Excavation of the pipeline-trench in consideration of standards and UVV | • | ||||
| 24 | Wall penetrations at the houses of the users | • | ||||
| 25 | Delivery of isoplus material | • | ||||
| 26 | Unloading and weather proof storage of isoplus material | • | ||||
| 27 | Draining of pipe trench and keeping it free until refilling | • | ||||
| 28 | Building site instruction by isoplus representative, after request | • | ||||
| 29 | Preparation of trench-bottom, placing of PU-bars, wooden bars or sand sacks | • | ||||
| 30 | Laying of isoplus pipes according to trench design in lengths and heights | • | ||||
| 31 | Information to isoplus in case of any modifications and wait for static acceptance | • | • | • | ||
| 32 | Visit of building site, discussion in order to find a solution in case of modification | • | • | • | ||
| 33 | Placing and connection of medium pipes and fittings according to standard | • | ||||
| 34 | If necessary concrete fix-points and wait for setting | • | ||||
| 35 | Controlling of medium pipe connections according to tender and standard | • | ||||
| 36 | Post insulation works at the jacket pipes connections | • | ||||
| 37 | Fixing of required expansion pads in accordance to design | • | ||||
| 38 | Eventual thermal pre-stressing (provide sand bridge) | • | • | |||
| 39 | Insert wall sealing into wall penetration and concrete | • | • | |||
| 40 | Acceptance of trench and approval for refilling by head of construction company | • | • | |||
| 41 | Sand filling up to 100 mm above pipe-top and compressing by hand | • | ||||
| 42 | Filling and compressing of trench from top of sand bed | • | ||||
| 43 | Heat shrinking of end caps at house-connections | • | ||||
| 44 | Installation of alarm wire-components | • | ||||
| 45 | Removing of remaining material and leaving of building site | • | • | • | ||
| 46 | Start of operation of pipe trench, handing over of documentation | • | • | • | • | • |
| 47 | Acceptance of authorities | • | • |